We track Haven's build every month using the developer's footage and the Government of Dubai's independent RERA progress reports, so owners and buyers get the honest picture, not marketing.
Is Haven on time? Yes. As of the latest RERA inspection (28 Jul 2026), all three Haven phases are audited as "Main Contract - Progressing." Enabling and foundation works are complete across the community, structures are rising, and Phase 3 is already at an advanced structural stage. Handover remains on schedule for Q3 2027.
RERA notes: enabling & foundation complete, structure at an advanced stage; internal works, external envelope, MEP, internal finishes and infrastructure all progressing on site. The furthest-advanced of the three phases.



RERA notes: enabling & foundation complete; structure, internal works, external envelope, MEP, internal finishes and infrastructure all progressing on site.



RERA notes: enabling & foundation complete; structure, internal works, external envelope, MEP and internal finishes progressing on site.